PERT and CPM MCQ Test

Following are mostly asked Pert and cpm MCQ test that are designed for professionals like you to crack you interviews. You can take this Pert and cpm online test before appearing to you real interview. This Pert and cpm quiz there are around 30+ multiple choice questions on Pert and cpm with four options.

1) What is PERT analysis based on?

  • A. Most likely time
  • B. Pessimistic time
  • C. Optimistic time
  • D. All of the above

2) What is the particular task performance in CPM known as?

  • A. Contract
  • B. Activity
  • C. Event
  • D. Dummy

3) What is a critical path?

  • A. It is the longest path
  • B. It is the shortest path
  • C. It is a mixture of all the paths
  • D. It is a path that operates from the starting node to the end node.

4) What is the completion of a CPM network diagram activity commonly known as?

  • A. Node
  • B. Event
  • C. Connector
  • D. All of the above

5) Activity in a network diagram is represented by?

  • A. Arrows
  • B. Circles
  • C. Squares
  • D. Rectangles
Download Free : PERT and CPM MCQ PDF

6) Who introduced the bar charts?

  • A. Joseph henry
  • B. Jane Gantt
  • C. Henry Gantt
  • D. Williams henry

7) The full form of PERT is ___________.

  • A. Program Evaluation and Robot Technique
  • B. Program Evaluation and Rate Technology
  • C. Program Evaluation and Review Technique
  • D. Program Evaluation and Robot Technology

8) The full form of CPM is ___________.

  • A. Control Path Method
  • B. Critical Path Method
  • C. Control Path Management
  • D. Critical Plan Management

9) A PERT network is activity-oriented while a CPM network is event-oriented.

  • A. False
  • B. True

10) _________ are used to represent activity in a network diagram.

  • A. Arrows
  • B. Rectangles
  • C. Squares
  • D. Circles

11) In a network, a critical path is the time-wise shortest path.

  • A. False
  • B. True

12) What does PERT analysis based on?

  • A. Optimistic
  • B. Pessimistic
  • C. Optimistic
  • D. All of the above

13) CPM was developed in which country?

  • A. Japan
  • B. China
  • C. Russia
  • D. USA

14) Slack time in PERT analysis.......

  • A. Is always zero for critical activities
  • B. Is minimum for critical events
  • C. Can never be greater than zero
  • D. Can never be less than zero

15) The earliest start time rule are:

  • A. Regulates when a project must begin
  • B. the activities starting time for an activity successor
  • C. the activities end time for an activity predecessor
  • D. Directs when a project can start